Final milling and paving activities are scheduled from August 4th to 9th.
The details of the closures to accommodate this work are as follows: Nightly, 9:00 pm to 5:30 am, Tuesday, August 4th to Thursday, August 6th, asphalt milling and temporary line markings
The paving operation is weather-dependent. The Saturday closures will be rescheduled to Sunday if work cannot proceed due to rain. Looking Ahead: Following the final paving operation, one eastbound and one westbound lane on Eastern Avenue will remain closed in a localized area between Sumach Street to St Lawrence Street to complete the Adelaide Bridge pier rehabilitation until fall 2026. Following this work, rehabilitation work on the underside of the bridges will continue, including intermittent short-term/overnight closures on Eastern Avenue, DVP, and the connecting ramps. Final restoration and plantings are scheduled to be completed in Spring/Summer 2027.